Environmental Impact Statement: Mid-Breton Sediment Diversion

Summary

The Coastal Protection and Restoration Authority (CPRA) has submitted a Joint Permit Application to the Department of the Army (DA) under the provisions of Section 404 of the Clean Water Act (33 U.S.C. 1344) (Section 404), and Section 10 of the Rivers and Harbors Appropriation Act of 1899, as amended (33 U.S.C. 403) (“Section 10”) and a permission request under Section 14 (33 U.S.C. 408) (Section 408) of the Rivers and Harbors Act of 1899 to the U.S. Army Corps of Engineers (“USACE”), at the New Orleans District (CEMVN) for CPRA’s proposed Mid-Breton Sediment Diversion  ( Proposed Action). 

An Environmental Impact Statement (EIS) will be prepared to disclose and analyze all significant environmental impacts of the Proposed Action as required under the National Environmental Policy Act (NEPA) in accordance with the Council on Environmental Quality’s (CEQ) regulations found in 40 CFR Parts 1500-1508.  This EIS will address the Public Interest Review requirements of 33 CFR Parts 320-332 including 33 CFR Part 325, Appendix B, 33 U.S.C. 408 and 40 CFR Part 230 (Section 404(b)(1) Guidelines), so that the EIS, when completed, will provide information required for an informed decision on the DA permit application and Section 408 permission request. Any additional information required for the Section 408 permission request beyond the completed final EIS will not be done by the selected third party contractor (TPC).

The Proposed Action generally consists of the placement of a sediment diversion through a portion of the federal Mississippi River and Tributaries (MR&T) Project mainline levee on the left descending bank of the Mississippi River (River) at approximately River Mile 68 and extending into the Mid-Breton Basin in Plaquemines Parish, Louisiana.

Below is a general EIS schedule for the major milestones.  Click here for the more detailed Mid-Breton Permitting Dashboard Schedule.  Please note, the EIS schedule is currently under development.  Once a schedule has been agreed on between USACE and the federal cooperating agencies, this webpage and the Permitting Dashboard will be updated.

EIS Milestones Target Date Completed Date
Permit Application Complete n/a 03/11/2019
Public Notice n/a 03/18/2019
Notice of Intent published in the Federal Register Jun 2020    07/02/2020
Scoping Meetings(s) Jul 2020    07/02/2020
Scoping Comment Period (End Date) Aug 2020    08/16/2020
Draft EIS availability announced in the Federal Register Jul 2024  
Public Meeting(s) on the Draft EIS Jul/Aug 2024  
Final EIS availability announced in the Federal Register Sep 2025  
Record of Decision

Apr 2026

 

Documents

Collapse All Expand All
 Initial Documents