Info

Collapse All Expand All
Expand List item 38949Collapse List item 38949  About

Public safety is the Corps of Engineers’ top priority. In lower Plaquemines Parish, Louisiana (LA), the level of risk reduction (LORR) against a storm surge event is provided by replacement or modification of certain portions of Non-Federal Levees (NFL) in Plaquemines Parish, Louisiana to be incorporated into the Federal project, and repair and restoration of the originally authorized New Orleans to Venice (NOV), LA Project.

Expand List item 38947Collapse List item 38947  Authorization 

The purpose of the originally authorized NOV, LA project is to achieve storm risk reduction for Plaquemines Parish by repairing and restoring the original project levees, accelerating the completion of unconstructed portions of the authorized project and armoring critical elements of the authorized project. The NOV Federal levees are located on the east bank of Plaquemines Parish, from Phoenix to Bohemia and on the west bank from St. Jude to Venice. Due to available funding limitations and constraints, a risk assessment was conducted in 2013 and updated in 2015 to distribute the funds in the most efficient manner and prioritize areas of deficiencies according to their level of risk. “Overtopping-without-Breach” is the principal risk driver for this project, and the analysis resulted in some changes of priority, primarily focusing efforts to implement improvements to raise low areas of the system mostly along the Mississippi River Levees (MRL). The NOV levees are being constructed to the 2%, 50-year LORR. The current NOV, LA project includes approximately 15 miles of back levee and MRL modifications, two sector gates on the west bank (near the Empire Floodgate and Empire Lock), fronting protection at existing pumping stations, and backflow prevention at two locations on the east bank (Bellevue and East Point a La Hache pumping stations) and at two locations on the west bank (Hayes and Gainard Woods pumping stations).

Expand List item 38948Collapse List item 38948  Project Status

Thirty construction contracts have been awarded. Twenty-five contracts have been completed. Five contracts are under construction. Construction is scheduled to be completed by 2028.  In the aftermath of the 2021 hurricane season, the Disaster Relief Supplemental Appropriation Act (DRSAA) of 2022 authorized $783M for the NOV, LA Project to achieve 50-year level of risk reduction for 10 levee reaches. (As of November 2025)

Plaquemines Parish Non-Federal Levees (NFL)

On the west bank, where the Federally-authorized West Bank and Vicinity, Louisiana Project ends in Oakville, there are levees extending southward that were previously constructed by Plaquemines Parish and private entities. The levees extend southward from Oakville to St. Jude. In the aftermath of the 2005 hurricane season, Congress authorized funding to replace and modify certain portions of the NFL, and to incorporate these levees into the NOV, LA project. The current NFL incorporated into the NOV, LA project includes approximately 34 miles of levee replacements or modifications and a tie-in to NOV levees at St. Jude. Due to available funding limitations and constraints, a risk assessment was conducted in 2013 and updated in 2015 to optimize the levee heights and minimize the consequences based on the risk analysis results. The Oakville to LaReussite levee will be constructed using the design criteria to provide a 50-Year Level of Risk Reduction (LORR). For the remaining NFL extending from LaReussite to St. Jude, designs will be optimized to a consistent/ prioritized 20-25 year LORR. Improvements along the existing NFL include levee and floodwalls, drainage structures, two pump stations, floodgates, armoring, as well as fronting protection at existing pumping stations.

Final EA #543

Finding of No Significant Impact (FONSI)
Environmental assessment #543

New right of way and mitigation for the New Orleans to Venice hurricane risk reduction project: incorporation of non-federal levees from Oakville to St. Jude and New Orleans to Venice Federal hurricane protection levee, Plaquemines Parish, Louisiana

Description of the Proposed Action: The U.S. Army Corps of Engineers (USACE), New Orleans District (CEMVN), has prepared Environmental Assessment (EA #543) to evaluate the potential impacts associated with proposed modifications to the right of way (ROW) necessary for the New Orleans to Venice Hurricane Risk Reduction Project: Incorporation of Non-Federal Levees (NFL) from Oakville to St. Jude and New Orleans to Venice Federal Hurricane Protection Levee (NOV HPL). (Col lectively referred to as "NFL NOV".) EA #543 also evaluates the potential impacts associated with completing compensatory mitigation for the impacts that would be incurred from construction of the NFL NOV projects using the previously identified ROW, as modified by the new ROW addressed in EA #543. As a resu lt of the NFL NOV projects, dry bottomland hardwoods (BLH-Dry), wetland bottomland hardwoods (BLH-Wet), scrub shrub, swamp, wet pasture, freshwater marsh, intermediate marsh, brackish marsh, saline marsh, and open water habitats are being impacted in the Barataria Basin.

Final Environmental Assessment #543 and Signed Finding of No Significant Impact
Appendix A Figures DCM
Appendix B Tables
Appendix E 2017-08-22, 401, 404 PN, Final 404(b)(1) Evaluation (Short Form)
Appendix F AEP Plan Selection Criteria LLW
Appendix G Public and Agency Comments and Response Summary
Appendix H WVA Model Assumptions
Appendix I Acronyms DCM
Appendix J Mitigation Planting, Monitoring and Related Guidelines DCM
Appendix K_Interagency Env Proj Delivery Team DCM
Appendix L Cumulative Impacts DCM
Appendix M Agency Coordination

 

Supplemental Information on #543: