Phase III – Uptown Napoleon Avenue
NEW ORLEANS -The U.S. Army Corps of Engineers, New Orleans District recently awarded a 38-month contract to provide increased drainage for the Uptown area. The contract includes canal improvements along Napoleon Avenue between Carondelet and Constance Streets. The project, which is part of the Southeast Louisiana Project (SELA), will reduce the risk of damages from a 10-year rainfall event. A 10-year event is basically a rain storm that has a 10% annual probability of occurrence and equates to approximately 9 inches of rain over a 24-hour period for our area.
On September 26, 2013, the Corps awarded a $38 million contract to Boh Bros Construction Co. The contract calls for constructing approximately 3,000 linear feet of a concrete covered box culvert under the neutral ground along Napoleon Avenue from Carondelet Street to Constance Street. The new culvert will parallel an existing box culvert and will tie in to the new culvert under Napoleon Avenue at Carondelet Street and the existing box culvert at Constance Street. A notice to proceed will be issued early October and construction will be completed in the fall of 2016.
The Corps continues to work closely with its partners at the Louisiana Coastal Protection and Restoration Authority and the Sewerage and Water Board of New Orleans on the SELA program. To date, a total of 17 contracts have been awarded in Orleans Parish to date, with work completed on 10 of those projects. All scheduled SELA work in Orleans Parish should be finished in 2018.

Release no. 13-060