New Orleans District presentation to
Ricky Boyett
Public Affairs, MVN 22 AUGUST 2023
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
2
HWY 61 AND KCS BRIDGE CONSTRUCTION W/ CHANNEL EXCAVATION
Construction includes two vehicular bridges and one Kansas City Southern railroad bridge spanning approximately 300 feet.
COM 01: 99% Complete
BROOKS LAKE
Brooks Lake design is currently at 95%.
COM 02
Traffic is currently traversing on new bridges.
COM 03
CHANNEL SEGMENT 01
Construction includes approximately 1.33 miles in length between Hwy 61 to the east and Bayou BR to the west
Contract solicitation was 9 August 23, with bids anticipated to open 7 Sept 23.
COM 04
BAYOU BATON ROUGE ROCK CHUTE
Construction includes approximately 1,500-foot-long rock chute and approximately 3500 feet of diversion channel connecting with Channel Segment One on the west and Channel
Segment 2A on the west.
COM 05: 85% Complete
Contract scheduled to award early 2024; awaiting relocation of utilities.
CHANNEL REACH 2A
. Construction includes approximately 1 mile of diversion channel between Hwy 964 on the west and Cypress Bayou on the east.
Construction is underway, with rip rap placement ongoing
COM 06: 30% Complete
CYPRESS BAYOU ROCK CHUTE
Construction includes approximately 1200 ft long rock chute and approximately 1900 ft of the diversion channel connecting channel segment 2A on the west and channel segment 2B on the east
COM 07-11: Complete
Construction is underway, with excavation of the channel ongoing.
CLEARING AND GRUBBING
CLEARING AND GRUBBING 3 BAYOUS
Contract award is scheduled late 2024
COM 12
WORK IS COMPLETE
3
COM 15
CHANNEL SEGMENT 3
Construction includes approximately 1 mile of diversion channel between Hwy 19 on west and McHugh Rd on the east.
Contract award awaiting utility relocation.
MCHUGH ROAD
.Construction includes a two-lane bridge that will cross the diversion channel.
COM 16: 99% Complete
Project is in closeout phase.
COM 17: 85% Complete
CHANNEL SEGMENT 04
Construction includes 1.5 miles of channel segment between McHugh Rd on west and LA Hwy 67 on the east
Construction is underway, with rip rap placement ongoing.
COM 18: 75% Complete
WHITE BAYOU
Construction includes 1300-foot-long rock chute and approximately 1400 feet of the diversion channel
Construction is underway, with Rip Rap placement ongoing.
COM 19
COMITE RIVER DIVERSION STRUCTURE
Construction includes a concrete structure that will allow flood waters to enter the diversion channel
Contract award awaiting completion of Hwy 67.
COM 20
CHANNEL SEGMENT 2B
Construction includes approximately 1,300 feet of diversion channel
MAINTENANCE WORK ON LILY BAYOU
Construction includes epoxy injections to fill concrete slab voids
COM 21: Complete
Contract award awaiting utility relocations.