What: Media are invited to observe construction of the Permanent Canal Closures & Pumps (PCCP) site at the 17th Street Canal from the
Interim Closure Structure. Current construction activities include pile driving, placement of rock slope protection around the bypass gate structure, sand push across the canal channel, installation of hydraulic piping on bypass gate structure, installation of reinforcing steel on the west floodwall and installation of the open cell cofferdam.
When / Where: Wednesday, August 13, 2014
10:00 – 11:00 AM
17th Street Interim Closure Structure (East Side)
Who: LTC Austin Appleton, Deputy Commander for the New Orleans District, will be available for the tour and follow on interviews.
Planning to attend: Media interested in attending should RSVP via telephone to (504) 862-1495 or
(504) 715-1661 no later than 5 pm on Tuesday, Aug. 12. This event is not open to the public.
Note to Media: Participants must comply with the following dress code:
• Long Pants
• Short-Sleeve Shirts - No tank tops, no muscle shirts.
• Non-Skid Shoes - No open toes, no sandals, no high heels.
: The Corps awarded the approximately $615 million contract to construct Permanent Canal Closures & Pumps (PCCP) at the mouths of the 17th Street, Orleans Avenue and London Avenue outfall canals on April 17, 2013 to PCCP Constructors JV. The PCCP will provide a permanent and more sustainable measure for reducing the risk of a 100-year level storm surge entering the outfall canals. The Interim Closure Structures (ICS) will continue to provide 100-year levels of storm surge risk reduction until the PCCP are constructed and commissioned in 2017.
For more information on the PCCP project:
Web site: www.mvn.usace.army.mil/Missions/HSDRRS/PCCP.aspx
Facebook: www.facebook.com/PermPumps
Construction Hotline: (877) 427-0345 | Flickr: www.flickr.com/photos/teamneworleans/sets/72157636355167283/
Release no. 14-043