Corps Logo                         

Project Fact Sheet   Morganza


Project Fact Sheet 


Printable Version       

Morganza, Louisiana to the Gulf of Mexico Risk Reduction Project

Purpose. Reduce hurricane and flood damages in an environmentally sustainable manner in the Houma area. The project will protect over 150,000 people and 130 square miles of saline and fresh marshes, farmlands, heavy and light industry, residential, and other developed areas. Protect development and the remaining fragile marsh from hurricane storm surge. 

Location. Coastal Louisiana approximately 60 miles southwest of New Orleans, and includes portions of Terrebonne and Lafourche Parishes. The area is bounded on the west by Bayou Du Large and State Highway 311 and on the east by Bayou Lafourche. The southern boundary is the Gulf of Mexico.

Sponsors. The Louisiana Department of Transportation and Development (LADOTD) acted as the local sponsor for the feasibility study and has been replaced by the Louisiana Coastal Protection and Restoration Agency (LACPRA) who has agreed to sponsor detailed design and construction. Terrebonne Levee and Conservation District (TLCD) will provide Operation, Maintenance, Repair, Rehabilitation and Replacement (OMRR&R). 

Authority. A Reconnaissance Study for the Morganza, Louisiana to the Gulf of Mexico Risk Reduction Project was authorized by Congress in 1992. Following completion of this report, Congress authorized a Feasibility Study in the Energy and Water Development Appropriations Act of 1995 (Public Law 103-316). The Feasibility Study was completed in March 2002 and the Chief of Engineers letter was forwarded to the Secretary of the Army in August 2002 and supplemented in July 2003. 

Features. Approximately 72-miles of earthen levee, ten 56-foot wide (sector gate) navigable floodgates, three 125-foot wide (sector gate) navigable floodgates, 12-multi barrel water control structures, 13-tidal exchange structures and a lock complex consisting of a lock in the Houma Navigation Canal measuring 110-feet by 800-feet, an adjoining navigable floodgate (sector gate) measuring 250 feet wide, and a dam closure. The structural features are integrated into the levee alignment to provide flood protection, drainage, environmental benefits, and navigational passage. Construction of this plan is estimated to cost $912 million (2007 price level) and would be cost shared 65% / 35% with LADOTD, the local sponsor. 

Costs

Total Project (2007 price level)

Total Project Cost

$912,000,000

Total Federal Cost 

$592,800,000

Total Non-Federal Cost 

$319,200,000

Schedule. The feasibility report was completed in March 2002. The Chief’s Report was signed on 23 August 2002. Preliminary Engineering and Design (PED) for the Houma Navigation Canal lock is ongoing and scheduled to be completed in December 2009. PED for the additional project features is also ongoing and scheduled to be completed in FY 10. 

Issues. NA

Hurricane & Emergency Web Page
http://www.mvn.usace.army.mil/pao/response/index.asp

 

Updated: February 22, 2008