NOTE: This is a tentative construction schedule as of August 25, 2004. All dates are approximate and subject to change, and are pending adequate funding levels.

 

PROJECT FEATURE START FINISH

 

Florida Avenue Bridge Replacement
  • Construction being done by Port of New Orleans
  • December 2000 September 2004

     

    Demolition and Site Preparation
  • East Bank Industrial Area Remediation
  • January 2001 March 2005
  • Galvez Street Wharf Demolition
  • May 2001 February 2003
  • Coast Guard Demolition
  • September 2008 September 2009

     

    Levees & Floodwalls
  • West Bank, Phase 1 (St. Claude Avenue to Mississippi River)
  • March 2005 January 2006
  • East Bank Levee Test Section
  • October 2002 June 2003
  • East Bank, Phase 1 (St. Claude Avenue to Mississippi River)
  • November 2006 October 2007
  • East Bank, Phase 2 (St. Claude Avenue to Claiborne Avenue)
  • July 2007 August 2008
  • West Bank, Phase 2 (St. Claude Avenue to New Lock)
  • January 2011 April 2012
  • East Bank, Phase 3 (Claiborne Avenue to New Lock)
  • May 2011 July 2012

     

    New Lock Construction
  • Phase 1 Dredging (bypass channel & lock site)
  • August 2006 July 2008
  • Lock Construction
  • October 2008 October 2012

     

    Claiborne Avenue Bridge Replacement
  • Bridge Construction
  • February 2011 August 2012

     

    St. Claude Bridge & Existing Lock Demolition
  • Build Temporary Bridge
  • May 2012 November 2012
  • Phase 2 Dredging (bypass channel)
  • December 2012 June 2013
  • Demolition of Lock and Bridge
  • January 2013 July 2014
  • Build New Bridge and Remove Temporary Bridge
  • June 2014 February 2015
  • Phase 3 Dredging (fore bay)
  • February 2015 May 2015

     

    Mooring Facilities
  • Construction of Mooring Facilities
  • June 2012 November 2013


     