![]()
|
|||||||||
|
|||||||||
|
Project Fact Sheet |
|||||||||
|
Updated August 23, 2005 PURPOSE.
Replace
the Inner Harbor Navigation Canal (Industrial Canal) Lock
with a larger, modern lock because the existing lock is too
small and congested, causing delays to traffic, which is
primarily inland navigation such as barges and towboats. LOCATION.
In New Orleans on the Industrial Canal at the Mississippi
River. The lock links the eastbound Gulf Intracoastal
Waterway (GIWW) to the Mississippi River, and thence to the
westbound Gulf Intracoastal Waterway through the nearby
Algiers and Harvey locks in the New Orleans area. SPONSORS.
The
federal government (Corps of Engineers and Inland Waterways
Trust Fund) is responsible for the inland (shallow-draft)
navigation portion of the project. The Port of New Orleans
and the federal government are sharing the costs of the
deep-draft navigation portion, as described below. AUTHORIZATION.
The Industrial Canal Lock Replacement Project is authorized
by the River and Harbor Act of 1956 (PL 84-455) and the
Water Resources Development Acts of 1986 (PL 99-662), which
reauthorized the project and established cost-sharing
requirements, and 1996 (PL 104-303), which authorized the
Community Impact Mitigation Plan. FEATURES.
The recommended plan is for a deep-draft lock, 110 feet wide
by 1,200 feet long by 36 feet of draft.
The lock construction would use a pre-fabricated, float-in
method. Five lock modules of concrete and steel would be
built at a remote location and floated to the
north-of-Claiborne-Avenue site. Movement of the barges will
be facilitated by the 300-foot horizontal clearance of the
Port of New Orleans and U.S. Coast Guard bridge at Florida
Avenue completed in 2005. The modular float-in method allows
for construction in a highly congested urban area with ZERO
residential relocations. Bypass channels will be built to
allow navigation to continue during construction. ISSUES.
The current lock, placed in service in 1921, is too small to
accommodate the existing traffic: 640 feet long, 75 feet
wide and 31.5 feet deep. The average delay to navigation is
11 hours, but can be as much as 24 to 36 hours on many
occasions. A highly urbanized area surrounds the lock on
both sides of the canal. The canal can't be shut down for
long periods of time without major impact to the navigation
industry. STATUS. Construction
has been completed for demolition and environmental
restoration of the abandoned industrial sites on the east
side of the canal adjacent to the future location of the new
lock. The $29 million contract, let to Washington Group,
involved removal of aboveground and underground structures
and canalside obstructions, and also extensive environmental
restoration. The area, visible from the A
contract for the design of the lock and related features
was awarded to URS Corp. in May 2002. Work on the contract
began in February 2003. The
real estate was purchased from the Port of New Orleans for
$16.8 million. The final act of sale took place Dec. 19,
2002. On July 30, 2005, the Corps began to collect soil, sediment and water samples in the canal to insure the proper management of material that will be dredged later in the lock project. News release. FUNDING.
For fiscal year 2005, the President’s budget was $10
million, and our capability was $24 million, and Congress
appropriated $14 million. For fiscal year 2006, the
President’s budget is zero and our capability is $25
million. COMMUNITY
IMPACT MITIGATION PLAN. Construction will impact nationally registered historic districts,
community cohesion and aesthetics, traffic, and businesses
in the area, but no residences will be relocated. This is
the basis for the $45 million Community Impact Mitigation
Plan, which was authorized by Congress in the Water
Resources Development Act of 1996. The mitigation plan
includes, but is not limited to, police protection, job
training, reimbursement of business’ lost revenue, street
improvements, housing revitalization program, educational
enhancements, parks and playgrounds, historical/cultural
markers and displays, and emergency medical services. Work
with various neighborhood organizations and individuals
identified these items over a number of years. The
Corps awarded a contract on September 1999 to a team of
consultants headed by GCR & Associates (other members
are Metro-Source LLC, University of New Orleans College of
Urban Affairs and Habitat for Humanity) to establish a
community-based committee. This is a multi-year contract and
will continue to involve the public in the implementation of
the mitigation plan. The team has set up the community-based
committee, executed a partnering agreement, and began the
regular meetings in early March 2000. A needs assessment and
a proposed mitigation plan for the first three years of
construction was completed in July 2000, which has now been
updated to January 2005. The Corps is at present developing
implementation strategies for the recommendations. The
Committee will continue to meet to update and refine its
recommendations. For
the first mitigation project, the Corps awarded a contract
for a job-training program, which was set-aside for a
Historically Black College/University, to Xavier University
in August 2000. This contract was geared to job-readiness
and basic construction skills and two classes have graduated
from the program. A separate job-training contract
focusing on specific construction skills was awarded to
Nunez Community College in December 2002. Four classes have
graduated from this program, in either electrical,
construction or welding. We
negotiated a partnering agreement in April 2004 with the
Friends of NORD (New Orleans Recreation Department) for
improvements to playgrounds in the impacted area. Under an
agreement with the New Orleans Police Department, more police
officers
began patrols in the Lower 9th Ward in May 2003.
Communication systems at the bridges crossing the Industrial
Canal and at the existing lock have been installed to allow
police and emergency medical vehicles to contact the bridges
and lock for status reports on openings. And, we signed an
agreement in May 2005 with the City of New Orleans
Sanitation Department to clean up vacant lots in the
impacted area. BACKGROUND.
Congress
approved the project as a “Construction New-Start” in
fiscal year 1999.The recommended plan is estimated to cost
$764 million in current dollars. The cost of a lock sized
just for inland navigation (110 feet wide by 900 feet long
by 22 feet deep) will be cost shared 50-50 between the
Inland Waterway Trust Fund and the regular Corps
appropriations. The remaining costs for the recommended plan
will be cost shared 65-35 between the Corps and the Port of
New Orleans. Included, as part of the inland navigation
increment, is the $45 million for the Community Impact
Mitigation Plan. Some of the existing utility owners will
have to pay for their own relocations, as they are
non-compensable. The costs reflect October 2004 price
levels:
COSTS, in millions
Average
annual benefits in the form of savings in transportation
costs for the nation’s navigation industry is estimated at
$110 million. The benefit-to-cost ratio is 2.0 to 1. Besides
the benefits to the navigation industry, this project will
have benefits to the city, region and state that are not
captured in our analysis. An average of at least 950 jobs
annually can be created as a result of construction of this
project. The city will get two new, more reliable bridges at
St. Claude and North Claiborne avenues. The project will
have significant, wide-ranging, positive economic impacts to
the city and the state, as has been the case with similar
projects in other areas. For example, estimates include an
additional $1.4 billion in secondary spending in the
metropolitan New Orleans area during the construction
period, and the generation of another $23 million in local
and state tax revenues during this period. |
|||||||||
|
|
|||||||||