Construction Sequence
Years 2001-2004
- Removal of East Bank Industrial Area, Galvez Street Wharf, Oak Trees, and U.S.
Coast Guard building.
- Levee and Floodwall construction begins.
- Bypass Channel around New Lock location is dredged.
Years 2004-2008
- Construction of New Lock is completed.
- Levees and Floodwalls are complete.
- The superstructure of the Claiborne Avenue Bridge is replaced with only a two-week
closure for vehicular traffic crossing the bridge.
Years 2007-2011
- Temporary Bridge at St. Claude Avenue while new bridge is under construction.
- Bypass Channel around existing lock.
- Existing lock is demolished.
Years 2011-2013
- New St. Claude Bridge is built.
- Mooring facilities built.
- Project Complete