INDUSTRIAL CANAL LOCK REPLACEMENT PROJECT
Skip both menus
Skip main menu
ABOUT IHNC
Skip PROJECT DETAILS submenu
Untitled Document
Project Features |
Project Schedule |
Construction Sequence
Project Schedule
NOTE: This is a tentative construction schedule as of June 5, 2003. All dates are
approximate and subject to change, and are pending adequate funding levels.
Florida Avenue Bridge Replacement
Construction being done by Port of New Orleans
December 2000 - September 2004
Demolition and Site Preparation
East Bank Industrial Area Remediation
January 2001 - December 2003
Galvez Street Wharf Demolition
May 2001 - February 2003
Coast Guard Demolition
September 2005 - September 2006
Levees & Floodwalls
West Bank, Phase 1 (St. Claude Avenue to Mississippi River)
June 2003 - April 2004
East Bank Levee Test Section
October 2002 - June 2003
East Bank, Phase 1 (St. Claude Avenue to Mississippi River)
January 2004 - December 2004
East Bank, Phase 2 (St. Claude Avenue to Claiborne Avenue)
June 2005 - July 2006
West Bank, Phase 2 (St. Claude Avenue to New Lock)
September 2007 - December 2008
East Bank, Phase 3 (Claiborne Avenue to New Lock)
May 2010 - July 2011
New Lock Construction
Phase 1 Dredging (bypass channel & lock site)
January 2005 - December 2006
Lock Construction
October 2006 - October 2010
Claiborne Avenue Bridge Replacement
Bridge Construction
February 2011 - August 2012
St. Claude Bridge & Existing Lock Demolition
Build Temporary Bridge
May 2012 - November 2012
Phase 2 Dredging (bypass channel)
December 2012 - June 2013
Demolition of Lock and Bridge
January 2013 - July 2014
Build New Bridge and Remove Temporary Bridge
June 2014 - February 2015
Phase 3 Dredging (fore bay)
February 2015 - May 2015
Mooring Facilities
Construction of Mooring Facilities
June 2012 - November 2013