Please click on the respective link for the description and status of the various project features. East Bank Industrial Area Remediation Demolition of Galvez St. Wharf West Bank Levee & Floodwall, Phase 1 East Bank Levee & Floodwall, Phase 1 East Bank Levee & Floodwall, Phase 2 West Bank Levee & Floodwall, Phase 2 East Bank Levee & Floodwall, Phase 3 Install 7 casings, 9 test piles and 48 reaction piles. Test for noise
and vibration reduction, and load bearing. Leveling and clearing of abandoned industrial sites on east bank,
between floodwall and canal, North Claiborne Avenue to Florida Avenue.
Contractor: Washington Group International, Inc. Demolition, removal and disposal of the Galvez Street Wharf, warehouse
and adjacent storeroom. Most of the debris will be removed by barge. On
canal's west bank, roughly between North Derbigny and North Tonti streets.
Most of the debris will be moved by barge.
Contractor: Virginia Wrecking Company, Inc. (The contractor is
a small business). Existing levee to be enlarged to 22.4 feet above sea level with 1,300
linear feet of earthen levee and 300 linear feet of combination earthen
embankment and I-type floodwall. Pedestrian walkway and benches provided.
On west bank of Industrial Canal from St. Claude Avenue to Mississippi
River. As part of the design of the project's levees and floodwalls, a short
levee test section (150-200 feet long) will be built on east bank of
Industrial Canal, just north of existing lock. St. Claude Avenue to Mississippi River. St. Claude Avenue to Claiborne Avenue. Removal of Coast Guard buildings between St. Claude and North
Claiborne avenues. Most of the debris will be removed by barge. Offsite fabrication of 4-lane, center-span and lift works for existing
North Claiborne Avenue Bridge. Float in components by barge. Offsite fabrication for 1,200 by 110-foot lock. Float in modules by
barge. Install between North Claiborne and Florida avenues. At new lock and bypass channel between North Claiborne and Florida
avenues. Dredged material placed by pipeline in disposal site on south
bank of the Mississippi River-Gulf Outlet. St. Claude Avenue to new lock. Claiborne Avenue to New Lock. Project Feature Information
Test Piles
Contractor: Boh Bros. Construction Co., LLC
Contract Amount: $1.6 million
Start: December 1999.
Construction Period: Completed, May 2000.
COMPLETED
PILE DRIVINGEast Bank Industrial Area Remediation
Contract Amount: $22.4 million
Contact Person: Dennis O'Conner, Project Manager, 947-5900
Start: January 2001.
Construction Period: 35 months.
CONSTRUCTION UNDERWAY
*TRUCK USE
*Truck traffic is kept behind an existing floodwall and directed to the
Florida Avenue bridge, to Poland Avenue and out to I-10.Demolition of Galvez St. Wharf
Contract Amount: $2.6 million
Contact Person: To be determined
Start: May 2001.
Construction Period: 21 months.
CONSTRUCTION UNDERWAY
*TRUCK USE
*Truck traffic is restricted to N. Galvez Street to Poland Avenue
and out to I-10.West Bank Levee & Floodwall, Phase 1
Estimated Start: June 2003.
Construction Period: 10 months.
DESIGN BEING COMPLETED
PILE DRIVING
TRUCK USEEast Bank Levee Test Section
Estimated Start: October 2002.
Construction Period: 8 months.
DESIGN BEING COMPLETED
TRUCK USEEast Bank Levee & Floodwall, Phase 1
Estimated Start: January 2004.
Construction Period: 11 months.
PILE DRIVING
TRUCK USEEast Bank Levee & Floodwall, Phase 2
Estimated Start: June 2005.
Construction Period: 13 months.
PILE DRIVING
TRUCK USECoast Guard Demolition
Estimated Start: September 2005.
Construction Period: 12 months.
TRUCK USE
Claiborne Avenue Bridge
Estimated Start: February 2011.
On-site installation: 2 weeks, August 2012.Lock Construction
Estimated Start: October 2006.
Construction Period: 48 months.
PILE DRIVING
TRUCK USE
Dredging, Phase 1
Estimated Start: January 2005.
Construction Period: 23 months.West Bank Levee & Floodwall, Phase 2
Estimated Start: September 2007.
Construction Period: 15 months.
PILE DRIVING
TRUCK USEEast Bank Levee & Floodwall, Phase 3
Estimated Start: May 2010.
Construction Period: 14 months.
PILE DRIVING
TRUCK USELater Project Components
Estimated Completion: WINTER 2013