|
Project Fact Sheet
|
Updated Aug. 18, 2004
PURPOSE.
Provide protection from
hurricane tidal overflow for 100-year frequency storms in the lower Mississippi
River delta region. It protects about 75 percent of the population and 75
percent of the improved lands in the project area.
LOCATION. The project
straddles the Mississippi River in Plaquemines Parish. On the east bank, the
project extends 16 miles from Phoenix down to Bohemia. On the west bank it
extends 34 miles from St. Jude to Venice. Maps, by
levee district: http://www.mvn.usace.army.mil/pao/response/amaps.asp
SPONSOR.
Plaquemines Parish Government. Costs are shared 70 percent federal, 30 percent
non-federal. Map
of Louisiana levee districts: http://www.mvn.usace.army.mil/pao/response/LeveeDistrictMap.asp
AUTHORITY.
The project was authorized by the
Flood Control Act of 1962 (PL 87-874) as the Mississippi River Delta at and
below New Orleans, La. Later it was changed to the New Orleans to Venice, La.,
Hurricane Protection Project.
WEST
BANK FEATURES:
St.
Jude to City Price. Three miles of enlarged back levees
Reach A. 13 miles of enlarged back levees from City Price to Tropical Bend and two 54-Iinch" flap-gated culverts
Reach
B-1. 12 miles of enlarged back levees from Tropical Bend to Fort Jackson and a
floodgate at Empire
Reach
B-2. Nine miles of enlarged back levees from Fort Jackson to Venice
West Bank River Levee (WBRL). 34 miles of enlarged west bank Mississippi River levees from City Price to Venice
EAST BANK FEATURES:
Reach
C. 16 miles of enlarged back levees from Phoenix to Bohemia and 10 flap-gated
culverts
COSTS:
Total
$254 million
Federal
177
million
Non-federal
77 million
STATUS. The project is
about 80 percent physically complete. The estimated completion date is September
2018. Status and estimated
completion date of each reach are:
Reach
Percent complete
Physical completion
St.
Jude-City Price
60
December 2005
Reach A
99
October 2012
Reach B-1
92
September 2013
Reach B-2
99
January 2011
Reach C
90
February 2008
West Bank River Levee
60
September 2018
We awarded the West Bank River Levee, Station 1319-1797, 2nd
Enlargement contract in September 2002.
FUNDING. For
fiscal year 05, the President’s budget is $2.97 million, and our capability is
$6.6 million.
Funding constraints will continue to slow down work on the project and
extend the project completion date.
BACKGROUND. Construction
was accelerated at the request of Plaquemines Parish Government so that the
levee could be raised sufficiently that the Federal Emergency Management Agency
(FEMA) would grant relief on the base slab elevation requirements for flood
insurance. As a result, flood insurance may now be obtained for property in some
areas with a slab elevation as low as ‑4.5 feet NGVD, instead of the
previously required +13.5 feet NGVD.
The area between St. Jude and City Price was incorporated into the
project at the request of Plaquemines Parish. The area provides a tie-in levee
at St. Jude in lieu of City Price. Costs for this work are 100 percent
non-federal and do not count towards the parish’s 30 percent contribution.
However, Plaquemines Parish was given credit for the part of the authorized
project that was not constructed.
Mitigation
to compensate for project-associated wetland losses on Reach B has been
constructed. This consists of five crevasses in the Mississippi River Delta to
promote marsh creation (one constructed in 1986 and the other four in 1995).
The remaining mitigation, for Reaches A, C, and WBRL, consisted of
creating and preserving marsh in the Pass à Loutre State Waterfowl Management
Area and was completed in 1997.
In
1987,the New Orleans District redesigned Reach A to incorporate the use of
geotextile fabric in levee construction. The redesign reduced right of way and
construction costs and resulted in savings of $35 million to $40 million of the
total project cost.
Contact
John Hall
Public Affairs Office
New Orleans, La.
504-862-2201
John.Hall@usace.army.mil