| Project
Fact Sheet
|
|
Updated
PURPOSE. Replace the
LOCATION. In
SPONSORS. The federal
government (Corps of Engineers and Inland Waterways Trust Fund) is
responsible for the inland (shallow-draft) navigation portion of the
project. The AUTHORIZATION. The
Industrial Canal Lock Replacement Project is authorized by the River
and Harbor Act of 1956 (PL 84-455) and the Water Resources
Development Acts of 1986 (PL 99-662), which reauthorized the project
and established cost-sharing requirements, and 1996 (PL 104-303),
which authorized the Community Impact Mitigation Plan.
ISSUES. The current
lock, placed in service in 1921, is too small to accommodate the
existing traffic: 640 feet long, 75 feet wide and 31.5 feet deep.
The average delay to navigation is 11 hours, but can be as much as
24 to 36 hours on many occasions. A highly urbanized area surrounds
the lock on both sides of the canal. The canal can't be shut down
for long periods of time without major impact to the navigation
industry. STATUS. Construction is well underway for demolition and
environmental restoration of abandoned industrial sites on the east
side of the canal adjacent to the new lock’s future location. The
contractor, Washington Group, has demolished all of the aboveground
structures. Underground structures and canal-side obstructions are
now being removed. The contract is scheduled for completion in March
2005. A second construction contract, for demolition of the
A contract for the design of the lock and appurtenant
features was awarded to URS Corp. in May 2002. Work on the contract
began in February 2003. The real estate was
purchased from the FUNDING. For
fiscal year 2005, the President’s budget is $10 million, and our
capability is $24 million. COMMUNITY IMPACT MITIGATION PLAN. Construction will impact nationally registered
historic districts, community cohesion and aesthetics, traffic, and
businesses in the area, but no residences will be relocated. This is
the basis for the $40 million Community Impact Mitigation Plan,
which was authorized by Congress in the Water Resources Development
Act of 1996. The mitigation plan includes, but is not limited to,
police protection, job training, reimbursement of business’ lost
revenue, street improvements, housing revitalization program,
educational enhancements, parks and playgrounds, historical/cultural
markers and displays, and emergency medical services. Work with
various neighborhood organizations and individuals identified these
items over a number of years. The Corps awarded a contract on September 1999 to a
team of consultants headed by GCR & Associates (other members
are Metro-Source LLC, University of New Orleans College of Urban
Affairs and Habitat for Humanity) to establish a community-based
committee. This is a multi-year contract and will continue to
involve the public in the implementation of the mitigation plan. The
team has set up the community-based committee, executed a partnering
agreement, and began the regular meetings in early March 2000. A
needs assessment and a proposed mitigation plan for the first three
years of construction was completed in July 2000, which has now been
updated to July 2003. The Corps is at present developing
implementation strategies for the recommendations. The Committee
will continue to meet to update and refine its
recommendations. For the first mitigation
project, the Corps awarded a contract for a job-training program,
which was set-aside for a Historically Black College/University, to
We negotiated a partnering agreement in April 2004
with the Friends of NORD (New Orleans Recreation Department) for
improvements to playgrounds in the impacted area. Under an
agreement with the New Orleans Police Department, more
police
officers began patrols in the Lower 9th Ward
in May 2003. Communication systems at the bridges crossing the
BRIDGES VS. TUNNELS.
Residents of St. Bernard Parish have expressed serious concerns with
the proposed bridges at St. Claude and We contracted with URS Corp. to investigate the
feasibility and costs of tunnels at each crossing. URS determined
that tunnel construction in this area is feasible, but identified
many impacts to surrounding areas and determined that the costs of
tunnels would be $150 million to $200 million more than the bridges
proposed. The study was completed in December 2001 at a cost of
$170,000. The Corps is performing in-house studies on the real
estate, utility relocation, operation and maintenance, and
mitigation costs associated with the tunnel alternatives. In
addition, we are developing the benefits to the vehicular and
navigation traffic associated with the fewer delays resulting from
tunnels. The Corps is working
with the New Orleans Regional Planning Commission, which has traffic
models of the area, to update our traffic data. We are also working
with the Louisiana Department of Transportation and Development and
the EXISTING TONNAGE.
Traffic volume through the existing lock has taken a decline
recently. We are working with the PROJECT FACTS:
Congress approved the
project as a “Construction New-Start” in fiscal year 1999.The
recommended plan is for a deep draft lock, 110 feet wide by 1,200
feet long by 36 feet of draft. It is estimated to cost $672 million
in current dollars. The cost of a lock sized just for inland
navigation (110 feet wide by 900 feet long by 22 feet deep) is $540
million. The latter cost will be cost shared 50-50 between the
Inland Waterway Trust Fund and the regular Corps appropriations. The
remaining costs for the recommended plan will be cost shared 65-35
between the Corps and the Corps of
Engineers appropriations $341
million Inland
Waterways Trust Fund 270
million 33
million Utility
owners (relocations)
28
million Average annual benefits
in the form of savings in transportation costs for the nation’s
navigation industry is estimated at $110 million. The
benefit-to-cost ratio is 2.0 to 1. Besides the benefits to the
navigation industry, this project will have benefits to the city,
region and state that are not captured in our analysis. An average
of at least 950 jobs annually can be created as a result of
construction of this project. The city will get two new, more
reliable bridges at St. Claude and The lock construction would be accomplished using a
pre-fabricated, float-in method, that involves building five lock
modules of concrete and steel at a remote location and floating them
to the north-of-Claiborne-Avenue site. This method allows us to
build this lock in a highly congested urban area with NO residential
relocations. Bypass channels will be built to allow navigation to
continue during
construction. |
|