FLOOD CONTROL AND COASTAL EMERGENGY Public Law 99, 84th Congress, approved 28 June 1955, and subsequent amendments authorize up to $15,000,000 to be expended on the repair or restoration of any flood control work during any one fiscal year.
Purpose
To provide continued flood protection.
Physical Data
Work items are authorized on an individual basis and grouped into subprojects. Items or subprojects completed, under construction, or authorized during FY 1976 are as follows:
Atchafalaya Basin. Levees setback and repairs to existing structures:Point Coupee Drainage Structure
Petite Prairie Levee Setback
Cross Bayou Levee Setback
Holloway Lake Levee Setback
Morganza Forebay Guide Levee
Progress of Work
Work completed in FY is tabulated on 2-38 Map .
Costs
Cost of works completed in FY are tabulated on 2-38 Map .