LAKE PONTCHARTRAIN & VICINITY, LOUISIANA
CONDITION OF IMPROVEMENT, 30 SEPTEMBER 1997
AUTHORIZATION:
The project was authorized by Flood Control Act of 1965, and
the Water Resources Acts of 1974, 1986, 1990, and 1992.
PROJECT:
The project provides for construction of the Lake Pontchartrain
High Level Plan and the Chalmette Area Plan. The project includes a new
levee parallel to and immediately north of U.S. Highway 61, between the
levee along the Jefferson-St. Charles Parish boundary and the east Bonnet
Carrel Spillway guide levee, an enlarged levee along the Jefferson Parish
Lakefront (including measures to intercept and convey drainage from the
land side slope of the project levees in Jefferson Parish), an enlarged
New Orleans Lakefront levee landward of the seawall, enlargement of existing
levees of the Inner Harbor Navigation Canal in New Orleans, a new levee
floodwall along the Lakefront extending from the floodwall at the New Orleans
Lakefront Airport to South Point, an enlarged levee from South Point to
the GIWW, a levee along and north of the Mississippi River-Gulf Outlet
and Gulf Intracoastal Waterway from the Inner Harbor Navigation Canal to
Chef Menteur, and a new levee from the Inner Harbor Navigation Canal Levee
along and on the south bank of the Mississippi River-Gulf Outlet to a point
approximately 2-1/2 miles northeast of Verret and then in a generally westerly
direction to the Mississippi River Levee near Caernarvon. The strengthened
Mandeville seawall on the north shore at present height. A new pumping
station and vertical lift gates for the Florida Avenue Complex are included
in this project. Mitigation for environmental damage will be provided by
a segmented rock breakwater along the Manchac Wildlife Refuge.
LOCAL COOPERATION:
Assurances are required for the two independently justified
plans. The Chalmette Area Plans local sponsors are the Orleans Levee District,
St. Bernard Parish Council and Lake Borgne Basin Levee District. The High
Levee Plans local sponsors are the Orleans Levee District for the New Orleans
East unit, the East Jefferson Levee Board for the Jefferson parish portion
of the New Orleans West unit and the Ponchartrain Levee District for the
St. Charles Parish portion of the New Orleans West Unit.
PROGRESS:
Funds to initiate pre-construction engineering and design were
appropriated in FY 1966, and funds to initiate conbtruction were appropriated
in FY 1967. The project is approximately 82 percent complete and the estimated
completion date is November 2013. The New Orleans East Unit is 90 percent
complete, with a completion date of September 2009. The New Orleans West
Unit is 15 percent complete with a completion date of November 2013. The
Mandeville Unit is 100% complete as of September 1995. The Chalmette Unit
is 98 percent complete with a completion date of September 2001.
The mitigation project was completed in December 1996.
COST:
The total estimate of the project cost fully funded is $712,000,000.
The remaining benefit-cost ratio is 3.4 to 1 at 3-1/4 percent.